Project Description

Roof Edge and Wall Base Flashing Repairs

Roof Edge Repair

  1. Cut back roof at edge metal on upper portion. 9′ x 9′ area.
  2. Furnished and installed new drip edge metal with a “sandwich” layer of smooth bitumen underneath.
  3. Spud perimeter tie in of repair area.
  4. Swept loose gravel from repair area.
  5. Furnished and installed inverted cap sheet over repair area and properly secured.
  6. Furnished and installed modified bitumen over repair area.
  7. Tied in new membrane to existing roof system.
  8. Furnished and installed 3 course at perimeter tie in.
  9. Spread swept gravel evenly over roof system.
  10. Removed and hauled away all debris generated by repair work.
  11. Cleaned and primed repair area.

Base Flashing Repair

  1. Swept loose gravel from repair area. 6′ x 12′ at wall base flashing.
  2. Cut back roof at wall turn up.
  3. Cleaned and primed repair area.
  4. Furnished and installed modified bitumen over repair area.
  5. Tied in new membrane to existing roof system.
  6. Removed and hauled away all debris generated by repair work.